Electricity works apology ~ updated 3 June

6 June 2017

in Uncategorized

A considerable programme of Electricity Works is being undertaken by Western Power Distribution (WPD), starting on Monday 6th February around the crossroads area. Details are here … Please look out both here and on social media for updates, especially on road closures, as the work progresses.

23.3.17: WPD have informed us that the next phase in Bakers Lane will commence on Tuesday 9th May.

25.4.17: WPD have contacted residents via this letter. Advance warning signs for the closure of Bakers Lane are in place.

3.5.17 : WPD confirm work starts on Bakers Lane this Tuesday 9 May. They are anticipating the third phase when Old Road will be closed between the crossroads and Walkers Acre to commence on 24 July and be finished by 18 August; they are waiting until the school holidays to help minimise the inconvenience.

4.6.17 : WPD have apologised for the over-running works in Bakers Lane following difficulties with the contractors.

 